Sprawling over some 14 acres on the west side of the main hospital site, J Mould (Reading) were appointed by CALA Homes to act as Principal Contractor and carry out an extensive asbestos removal project, followed by full demolition and crushing arisings to type 1 grading. During the works we also created a 2-acre temporary carpark. J Mould were engaged very early on with this project assisting CALA homes Planning team with pre demolition audits and construction phase plans aiding them with securing the discharge of the planning conditions.

Project constraints and challenges: Planning phases and access to the site to limit the impact of the live hospital. Asbestos removal within 1000m of underground service ducts and tunnels. Working closely with ecologist as the site had know bat roosts, badger setts and knotweed.