Client: Peach Street....
Project Value: £500K
Timespan: July 2018
Project Type: N/A

Due to its location within the town centre, weeks of pre-planning went in, regarding traffic management plans and road closures. Plant was delivered to site at 5am to avoid further disruption, as plant had to be delivered down a one way road the wrong way. The works involved 8 weeks of asbestos removal and large scheme of temporary works and steel retention against a listed building. A full scaffold screen encapsulated the entire works along the High Street. Environmental monitoring was in place during the works which included, vibration, sound and dust.

Key Team Members

Jay Mould General Manager

Richard Harris Demolition Manager

Mick Woodley Contracts Manager

Paul Satchell Asbestos Contracts Manager

Jeff Clarke Site Supervisor